Road recycling is in-situ stabilisation described by what it saves rather than how it works.
The method is the same (pulverise the existing pavement, mix in a binder, compact and reseal), but the reason a council or an asset owner chooses it is increasingly this: the materials for the new road are already there.
Accurate is an AustStab-accredited contractor. AustStab is the Pavement Recycling and Stabilisation Association, and recycling is in the name because that's the point.
Best suited for
How we work with you
Flexible ways to engage Accurate, depending on your project requirements.
Everything required to build the pavement from start to finish, self-delivered and handed over complete.
Plant and crew for the stabilisation step itself, working to your programme with your own resources alongside.
Up to 100% of the existing pavement. The old base course, the old seal, and in many cases the top of the subgrade become the new bound layer. Nothing is dug out or carted to landfill, and no new quarried material is brought in except the binder itself, at 2–5% by mass.
On a typical 350mm-deep council rehabilitation over 5,000m², that's approximately 3,000 tonnes of material that stays in the road instead of going to landfill, and approximately 3,000 tonnes of new material that never has to be quarried, crushed and trucked to site.
A dig-out on that same 5,000m² job means carting 3,000 tonnes out and 3,000 tonnes in. At 20 tonnes a truck, that's around 300 truck movements through the street: noise, road wear, traffic control, and diesel.
Road recycling replaces that with a stabiliser, a spreader, a water cart and rollers. The plant arrives, does the job, and leaves. On a residential street, that's a fortnight of disruption cut to a few days.

The environmental case
Industry figures put the greenhouse gas reduction from in-situ recycling versus reconstruction at more than 50%, driven by three things: no new quarried aggregate, no haulage of old material out or new material in, and a much shorter construction period.
The old base course, the old seal, and in many cases the top of the subgrade become the new bound layer.
A dig-out on a 5,000m² job means carting 3,000 tonnes out and 3,000 tonnes in, at 20 tonnes a truck.
ISO 14001 environmental management certification means those outcomes are managed and documented on every job, not assumed.
FAQs
You'll see the term cold in-place recycling (CIPR) used, especially in Queensland and by national contractors. It describes the same method Accurate delivers: the existing asphalt and base are milled and recycled in place, without heat, into a new bound layer.